Sorry, this page has moved!
Please click here to go to the new location.

Trabuco Creek Channel (L02) Levee Protection, Phase VII

TRABUCO CREEK CHANNEL (L02) LEVEE PROTECTION, PHASE VII

from
U/S OF L01 & L02 CONFLUENCE (STATION 17+25)
to
D/S OF DEL OBISPO STREET (STATION 44+45)

Advertisement:  March 05, 2013 
Bid Opening:  April 24, 2013 @ 2:00 P.M.
Award Date:  June 18, 2013
Start of Construction:  August 2013
Construction Duration:  300 Working Days
Contract Award:  $15,060,322.00

Project Information: 
The Trabuco Creek Channel (L02), is located in the City of San Juan Capistrano. Trabuco Creek Channel was built in 1962 as a soft-bottom trapezoidal channel with 4-inch thick unreinforced concrete lined walls (2:1 side slopes), and is a tributary to San Juan Creek Channel (L01). Extensive channel wall damage was sustained in 1998 due to major storms when approximately 325 feet of the channel embankment was partially washed out and temporarily flooded San Juan Capistrano’s City Hall, which is adjacent to the channel. In December 2010 additional channel wall and embankment damage was sustained due to storm flows.

Despite previous repairs, the channel remains vulnerable to levee failure. In response, OC Public Works developed an eight phase plan to be accomplished in seven years. Phase 7 proposes to install approximately 4,800 linear feet of a steel sheet pile wall system behind the unreinforced channel lining in order to reinforce the existing levee. A short flood wall will also be constructed on top of the steel sheet piles to meet FEMA freeboard requirements toward the eventual removal of nearby residents from the 100-year Flood Plain. 
  

Location:
City of San Juan Capistrano
Supervisorial District 5 
    
Construction Information: 
    
Contractor:  J.F. Shea Construction, Inc.   
Award:  $15,060,322.00
Start Date:  August 2013
Contact:  phone icon714-245-4500    
 
Bulletins/Addenda:

  1. Bulletin No. 1 [issued 4/19/13]

Bid Package:

  1. Notice to Contractors
  2. Special Provisions   [30.0 MB; download time will vary; alternately right-click & "Save Target As"]
  3. Construction Plans – Full-Size 22"x34"  [23.56 MB; download time will vary; alternately right-click & "Save Target As"]

Supporting Documents:

  1. Location Map 1
  2. Brief Project Description
  3. Geotechnical Report  [2.95 MB]
  4. Planholders List  [current as of 4/23/13]
  5. Pre-Bid Meeting Sign-In Sheet  [4/10/13]
  6. Labor Compliance / Prevailing Wage Sample Documents                     

                                           

Public Meeting:

Held On: March 23, 2011, 6:30 pm
Venue: Community Services Department – Community Hall 25925 Camino Del Avion San Juan Capistrano, CA 92675
Presentation:

Design Contacts: ENVELOPE ICON Hugo Pineda phone icon714-647-3973 ENVELOPE ICON Charles Busslinger phone icon714-647-3978  FAX IMAGE (714) 967-0884